Newtownmountkennedy Residential Development, Co. Wicklow

The Newtownmountkennedy Residential Development highlights how a collaborative, design-led approach can deliver effective retaining solutions for large-scale housing projects. The Alfarock Retaining Wall System provided the flexibility and performance needed to support successful delivery across this multi-phase development in Co. Wicklow.

The Challenge

The Newtownmountkennedy Residential Development is a large-scale housing scheme comprising 475 new homes in County Wicklow. The site presented significant engineering and construction challenges due to:

  • Steep and varying site levels across multiple phases.
  • The need to maximise developable land while maintaining stable earth retention.
  • Tight programme requirements across a large multi-phase residential development.
  • The requirement for a retaining solution that could be adapted to different wall heights and layouts while maintaining a consistent aesthetic appearance.
  • Coordination between the developer, consulting engineers and contractor to ensure efficient delivery throughout the project lifecycle.

Traditional retaining solutions would have required significant programme time, specialist installation and increased site disruption.

The Solution

The design and installation contractor Evogeo engaged with the project team during the early design stages, working closely with Dres Properties and POGA Associates to develop a comprehensive retaining wall strategy.

The Alfarock Retaining Wall System was selected due to its flexibility, structural performance and speed of installation. Through a design-led approach, retaining wall solutions were developed and detailed in-house, allowing the project team to progress efficiently from concept through to construction.

The solution provided:

  • Approximately 3,000 m² of retaining wall construction across four development phases.
  • A fully integrated turnkey package including design support, supply and technical assistance.
  • Flexibility to accommodate varying wall heights and complex site geometries.
  • A durable and aesthetically attractive retaining structure suitable for a premium residential development.
  • Additional application within the site's retention pond, demonstrating the versatility of the AR system.
The Result

The result was a streamlined construction process that enabled the client to meet both programme and engineering objectives.The Newtownmountkennedy development demonstrates how the Alfarock Retaining Wall System can successfully deliver large-scale earth retention solutions on complex residential sites. Through early collaboration, efficient design support and a flexible modular system, the project achieved a robust, attractive and cost-effective retaining solution across all phases of the development. 

Lessons Learned

Lessons Learned

Early Engagement Delivers Better Outcomes

Flexibility is Essential on Challenging Sites

Turnkey Support Simplifies Delivery

Stakeholders

Stakeholders

Design & Installation Contractor - Evogeo

Consulting Engineer - POGA Associates

Main Contractor - Dres Properties